Construction Weather: Not a Cloud in the Sky, 31oF - 50oF
The weather could not be more cooperative this week, as crews are still hard at it. At this point in the construction process much of what is going on is just more of the same: Bricks, Granite, and more bricks. Although activity can be seen all over the mall, there is a very focused effort at the 100 Block East where Parham Construction Company crews are clearing old bricks from the Central corridor as Ground Effects Masons are re-pointing the Drainage Runnels and Design Electric workers were getting all the new electric conduit in place. It is quite a swarm of activity!
In other news, one of our very own citizens has taken it upon themselves to share a few kinds words: