Construction Weather: Clear, 31oF - 55oF
As is usual these days, there is much activity on the construction process. Parham Construction continues to work on demolition and crews can be seen focusing their efforts on both the 100 East Block, as well as near the 3rd Street intersection. At 3rd Street there will be minor utility work as crews connect 2 water lines to create a looped system.
As announced last week in the post entitled "Tree Watch",crews from Waynesboro Landscape and Garden Center have begun installing the trees near Central Place.
The 500 East Block is finally recieving its fair share of pavers as crews work quickly to finish off the center corridor section. Completion is expected this week. Thanks to all the 500 Block East business who have been patient with the process!